2018–2023 BUILDING PLAN Progress


On November 6, 2018, Lexington County School District One voters, with more than 56% of the vote, voted for and passed a $365 million five-year building plan (2018–2023) that ensures that we can continue to offer our students the facilities they need now and in the future. 

This building plan includes updated safety and security systems at all district schools and facilities; three new schools to replace old schools and increase student capacity; two new elementary schools needed to accommodate student growth; renovations, additions and/or upgrades to 14 elementary schools, five middle schools, five high schools, the district's maintenance facility, technology center and community learning center; a new district transportation facility; and information technology equipment and furniture for Future Ready Classrooms at all schools.

Since the district understands that those same voters want to keep up with the progress of the building plan, we developed this webpage to do just that. This site enables voters to see what is currently happening at their child’s school and includes “before” photographs, the current phase taking place, photographs of that progress, etc. In fact, voters can click on the initials of their child’s school below and go directly to that school’s progress update.

What people are talking about...
Centerville Elementary School
Lexington Middle School

What’s happening now?


 

09-17-2019 

 

Lexington One receives final approval to purchase Lexington Middle School relocation site. Read more here.

 

07-16-2019 

 

Lexington District One Board approves purchase of White Knoll property.
Read more here.

 

05-21-2019 

 

Lexington District One amends option agreement for Lexington Middle relocation.
Read more here.

Click here for all news articles.
Click here for Architectural Selection Committee Meeting Minutes.

FAQs

Want to know how the projects impact your child’s school and community?


What’s happening at my location?

CSES, CSMS, CES, DES, FPES, GHS, GMS, GPS, LMES, LES, LHS, LMS, LTC, MGES, MGMS, MES, NPES, OGES, PES, PHS, PMS, PHES, PHMS, RBES, RBHS, RCES, SGES, WKES, WKHS, WKMS


New elementary school #18 in River Bluff attendance area
New elementary school #19 in White Knoll attendance area
New middle school in Pelion attendance area
New transportation facility
Maintenance facility
Rosenwald Community Learning Center
314 Main St. Gilbert
758 Magnolia St. Pelion
702 N. Lake Dr. Lexington

Carolina Springs Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
CSES - Bus canopy/sitework improvements
January 2019–design phase
CSES - Bus canopy/sitework improvements
CSES - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
CSES - New storage/equipment building
January 2019–design phase
CSES - New storage/equipment building
CSES - Replace folding partition and flooring in multi–purpose room
January 2019–design phase
CSES - Replace folding partition and flooring in multi–purpose room
CSES - Secure entry upgrades
Secure entry upgrades
January 2019–design phase
CSES - Upgrade interior finish
January 2019–design phase
CSES - Upgrade interior finish
CSES - Water heater replacement
January 2019–design phase
CSES - Water heater replacement
Carolina Springs Middle School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
CSMS - Additional bus drop canopy
Additional bus drop canopy
April 2020–design phase
CSMS - Classroom addition
Classroom addition
April 2020–design phase
CSMS - Future ready classrooms
Future ready classrooms
Summer 2020–design phase
CSMS - Lane widening
Lane widening
April 2020–design phase
CSMS - New fire alarm system and cafeteria lighting
New fire alarm system and cafeteria lighting
April 2020–design phase
CSMS - New storage/equipment building
New storage/equipment building
April 2020–design phase
CSMS - Secure entry upgrades
Secure entry upgrades
April 2020–design phase
Centerville Elementary School

Progress:
Administration recommends new Gilbert school name.
Groundbreaking for new Gilbert school held April 30, 2019.
New Gilbert school named Centerville Elementary.


Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
CES - Groundbreaking
May 2019
CES - Groundbreaking
CES - Land clearing
May 2019
CES - Land clearing
CES - Building
July 2019
CES - Building
CES - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
CES - Opening year
Opening year
2020–2021
Deerfield Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
DES - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
DES - Secure entry upgrades
Secure entry upgrades
January 2019–design phase
Forts Pond Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
FPES - Add exterior lighting in front parking area
Add exterior lighting in front parking area
Sept. 2020–design phase
FPES - Classroom addition
Classroom addition
Sept. 2020–design phase
FPES - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
FPES - New storage/equipment building
New storage/equipment building
Sept. 2020–design phase
FPES - Replace folding partition and flooring in multi–purpose room
Replace folding partition and flooring in multi–purpose room
Sept. 2020–design phase
FPES - Secure entry upgrades
Secure entry upgrades
Sept. 2020–design phase
Gilbert High School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
GHS - Add exterior hardscapes
Add exterior hardscapes
February 2019–design phase
GHS - Fire alarm system replacement
Fire alarm system replacement
February 2019–design phase
GHS - Future ready classrooms
Future ready classrooms
Summer 2020–design phase
GHS - Interior & Exterior finish upgrade
Interior & Exterior finish upgrade
February 2019–design phase
GHS - Program–based additions needed; PAC, weight, wrestling
Program–based additions needed; PAC, weight, wrestling
February 2019–design phase
GHS - Secure entry upgrades
Secure entry upgrades
February 2019–design phase
GHS - Upgrade interior/exterior lighting
Upgrade interior/exterior lighting
February 2019–design phase
Gilbert Middle School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
GMS - Additional visitor parking
Additional visitor parking
June 2020–design phase
GMS - Canopy needed at front entrance
Canopy needed at front entrance
June 2020–design phase
GMS - Classroom addition
Classroom addition
June 2020–design phase
GMS - Exterior security lighting upgrades
Exterior security lighting upgrades
June 2020–design phase
GMS - Fire alarm system replacement
Fire alarm system replacement
June 2020–design phase
GMS - Future ready classrooms
Future ready classrooms
Summer 2020–design phase
GMS - Interior finish upgrades
Interior finish upgrades
June 2020–design phase
GMS - New dishwasher, cooler, freezer
New dishwasher, cooler, freezer
June 2020–design phase
Gilbert Primary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
GPS - Add exterior canopies, walking track and hardscapes
Add exterior canopies, walking track and hardscapes
Dec. 2018–design phase
GPS - Add exterior canopies, walking track and hardscapes
GPS - Addition to existing storage/ equipment building
Addition to existing storage/ equipment building
Dec. 2018–design phase
GPS - Car/bus circulation updated
Car/bus circulation updated
Dec. 2018–design phase
GPS - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
GPS - HVAC controls improvement, water heater, exhaust hood
HVAC controls improvement, water heater, exhaust hood
Dec. 2018–design phase
GPS - Replace wood doors and add ADA compliant door hardware
Replace wood doors and add ADA compliant door hardware
Dec. 2018–design phase
GPS - Secure entry upgrades
Secure entry upgrades
Dec. 2018–design phase
GPS - Student restrooms renovation, ADA upgrades
Student restrooms renovation, ADA upgrades
Dec. 2018–design phase
GPS - Upgrade interior finish
Upgrade interior finish
Dec. 2018–design phase
GPS - Upgrade interior/exterior lighting
Upgrade interior/exterior lighting
Dec. 2018–design phase
Lake Murray Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
LMES - ADA upgrades to restrooms
ADA upgrades to restrooms
Sept. 2020–design phase
LMES - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
LMES - Roof replacement
Roof replacement
Sept. 2020–design phase
LMES - Storage/equipment building
Storage/equipment building
Sept. 2020–design phase
LMES - Upgrade cafeteria and stage lighting
Upgrade cafeteria and stage lighting
LMES - Upgrade exterior lighting, terraced wall, and hardscaping
Upgrade exterior lighting, terraced wall, and hardscaping
Sept. 2020–design phase
LMES - Upgrade interior finish
Upgrade interior finish
Sept. 2020–design phase
Lexington Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
LES - Demolish and remove old buildings
Demolish and remove old buildings
May 2021–design phase
LES - Future ready classrooms
Summer 2019–design phase
LES - Future ready classrooms
LES - New drop off/pick–up lanes
New drop off/pick–up lanes
May 2021–design phase
LES - Replace casework
Replace casework
May 2021–design phase
LES - Replace wood doors and add ADA compliant door hardware
Replace wood doors and add ADA compliant door hardware
May 2021–design phase
LES - Secure entry upgrades
Secure entry upgrades
May 2021–design phase
LES - Storage/equipment building
Storage/equipment building
May 2021–design phase
LES - Upgrade exterior lighting
Upgrade exterior lighting
May 2021–design phase
LES - Upgrade interior finish
Upgrade interior finish
May 2021–design phase
Lexington High School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
LHS - Replace classroom carpet with tile
Nov. 2018–design phase
LHS - Replace classroom carpet with tile
LHS - Future ready classrooms
Future ready classrooms
Summer 2020–design phase
LHS - New asphalt overlay
Nov. 2018–design phase
LHS - New asphalt overlay
LHS - New athletic storage buildings (2)
New athletic storage buildings (2)
Nov. 2018–design phase
LHS - Roof replacement
Nov. 2018–design phase
LHS - Roof replacement
LHS - Secure entry upgrades
Secure entry upgrades
Nov. 2018–design phase
LHS - Upgrade interior finish and new signage
Nov. 2018–design phase
LHS - Upgrade interior finish and new signage
Lexington Middle School

Relocation progress:
The Board of Trustees accepted the administration’s recommendation to enter into option agreements.
Lexington District One amends option agreement for Lexington Middle relocation.
Lexington District One receives final approval to purchase Lexington Middle School relocation site.

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
LMS - Groundbreaking
Groundbreaking
TBA
LMS - Land Clearing
Land Clearing
TBA
LMS - Opening year
Opening year
2021–2022
Lexington Technology Center

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
LTC - ADA restroom upgrades
ADA restroom upgrades
February 2019–design phase
LTC - Add canopies at welding labs and overlay asphalt at front
February 2019–design phase
LTC - Add canopies at welding labs and overlay asphalt at front
LTC - Exterior painting
Exterior painting
February 2019–design phase
LTC - Future ready classrooms
Future ready classrooms
Summer 2020–design phase
LTC - Renovate locker rooms
Renovate locker rooms
February 2019–design phase
LTC - Replace carpet in administration and cosmetology areas
Replace carpet in administration and cosmetology areas
February 2019–design phase
LTC - Replace old windows
Replace old windows
February 2019–design phase
LTC - Replace roll–up doors
Replace roll–up doors
February 2019–design phase
LTC - Secure entry upgrades
Secure entry upgrades
February 2019–design phase
Meadow Glen Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
MGES - Add storage/equipment building
Add storage/equipment building
June 2022–design phase
MGES - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
MGES - Secure entry upgrades
Secure entry upgrades
June 2022–design phase
Meadow Glen Middle School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
MGMS - Add storage/equipment building
Add storage/equipment building
June 2022–design phase
MGMS - Future ready classrooms
Future ready classrooms
Summer 2020–design phase
MGMS - Secure entry upgrades
Secure entry upgrades
June 2022–design phase
Midway Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
MES - Add storage/equipment building
Add storage/equipment building
June 2022–design phase
MES - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
MES - Replace fire alarm system
Replace fire alarm system
June 2022–design phase
MES - Upgrade interior finish
Upgrade interior finish
June 2022–design phase
MES - Upgrade Interior/exterior lighting
Upgrade Interior/exterior lighting
June 2022–design phase
New Providence Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
NPES - Add storage/equipment building
Add storage/equipment building
Nov. 2022–design phase
NPES - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
NPES - Repaint Corridors, Replace Folding Partition
Repaint Corridors, Replace Folding Partition
Nov. 2022–design phase
NPES - Secure entry upgrades
Secure entry upgrades
Nov. 2022–design phase
NPES - Update lighting controls
Update lighting controls
Nov. 2022–design phase
North Lake Dr. Lexington

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
NLD - Selective demolition and repurposing existing site
Selective demolition and repurposing existing site
Nov. 2020–design phase
Oak Grove Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
OGES - Add storage/equipment building
Add storage/equipment building
May 2019–design phase
OGES - Classroom/Fine Arts addition
Classroom/Fine Arts addition
May 2019–design phase
OGES - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
OGES - New exterior security lighting
New exterior security lighting
May 2019–design phase
OGES - New fire sprinkler system
New fire sprinkler system
May 2019–design phase
OGES - Replace fire alarm
Replace fire alarm
May 2019–design phase
OGES - Secure entry upgrades
Secure entry upgrades
May 2019–design phase
OGES - Sitework Improvements
Sitework Improvements
May 2019–design phase
OGES - Update student restrooms
Update student restrooms
May 2019–design phase
Pelion Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
PES - Add storage/equipment building
Add storage/equipment building
July 2019–design phase
PES - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
PES - Future ready classrooms
PES - Replace carpet in chorus room
Replace carpet in chorus room
July 2019–design phase
PES - Replace ceiling tiles and interior lighting
Replace ceiling tiles and interior lighting
July 2019–design phase
PES - Replace roof on latest addition
Replace roof on latest addition
July 2019–design phase
PES - Replace serving lines in kitchen
Replace serving lines in kitchen
July 2019–design phase
Pelion High School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
PHS - Add school store in commons area
Add school store in commons area
Dec. 2018–design phase
PHS - Add stadium visitor locker room
Add stadium visitor locker room
Dec. 2018–design phase
PHS - Future ready classrooms
Future ready classrooms
Summer 2020–design phase
PHS - New track locker room, concessions and restroom
New track locker room, concessions and restroom
Dec. 2018–design phase
PHS - New weight/wrestling room
New weight/wrestling room
Dec. 2018–design phase
PHS - Secure entry upgrades
Secure entry upgrades
Dec. 2018–design phase
PHS - Track modifications
Track modifications
Dec. 2018–design phase
PHS - Upgrade audio/lighting in auditorium
Upgrade audio/lighting in auditorium
Dec. 2018–design phase
PHS - Upgrade lighting in gym
Upgrade lighting in gym
Dec. 2018–design phase
Pelion Middle School

Progress: Groundbreaking for new Pelion school held April 30, 2019.

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
PMS - Replace and relocate
May 2019
PMS - Replace and relocate
May 2019
PMS - Groundbreaking
May 2019
PMS - Groundbreaking
May 2019
PMS - Clearing
May 2019
PMS - Clearing
July 2019
PMS - Building
July 2019
PMS - Building
PMS - Future ready classrooms
Future ready classrooms
Summer 2020–design phase
PMS - Opening year
Opening year
2021–2022
Pleasant Hill Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
PHES - Add kitchen loading dock
Add kitchen loading dock
August 2022–design phase
PHES - Add storage/equipment building
Add storage/equipment building
August 2022–design phase
PHES - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
PHES - Replace carpet in admin/ foyer with hard tile
Replace carpet in admin/ foyer with hard tile
August 2022–design phase
PHES - Replace carpet with sports flooring in the multi–purpose room
Replace carpet with sports flooring in the multi–purpose room
August 2022–design phase
PHES - Replace folding partition
Replace folding partition
August 2022–design phase
PHES - Secure entry upgrades
Secure entry upgrades
August 2022–design phase
Pleasant Hill Middle School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
PHMS - Add canopies and sidewalk
Add canopies and sidewalk
Nov. 2022–design phase
PHMS - Future ready classrooms
Future ready classrooms
Summer 2020–design phase
PHMS - Replace cafeteria lights
Replace cafeteria lights
Nov. 2022–design phase
PHMS - Secure entry upgrades
Secure entry upgrades
Nov. 2022–design phase
Red Bank Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
RBES - Add storage/equipment building
Add storage/equipment building
July 2019–design phase
RBES - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
RBES - Replace food service equipment
Replace food service equipment
July 2019–design phase
RBES - Replace wood doors and add ADA compliant door hardware
Replace wood doors and add ADA compliant door hardware
July 2019–design phase
RBES - Secure entry upgrades
Secure entry upgrades
July 2019–design phase
RBES - Upgrade student restrooms and interior finishes
Upgrade student restrooms and interior finishes
July 2019–design phase
River Bluff High School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
RBHS - Future ready classrooms
Future ready classrooms
Summer 2020–design phase
RBHS - Secure entry upgrades
Secure entry upgrades
January 2022–design phase
RBHS - Upgrade parking lot landscaping
Upgrade parking lot landscaping
January 2022–design phase
RBHS - Upgrade student canopy
Upgrade student canopy
January 2022–design phase
Rocky Creek Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
RCES - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
RCES - Secure entry upgrades
Secure entry upgrades
January 2019–design phase
Rosenwald Community Learning Center

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
RCLC - Ceiling upgrades
Ceiling upgrades
October 2020–design phase
RCLC - Future ready classrooms
Future ready classrooms
October 2020–design phase
RCLC - Secure entry
Secure entry
October 2020–design phase
RCLC - Walk–in cooler and serving line replacement
Walk–in cooler and serving line replacement
October 2020–design phase
Saxe Gotha Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
SGES - Add storage/equipment building
Add storage/equipment building
August 2021–design phase
SGES - Future ready classrooms
Summer 2019–design phase
SGES - Future ready classrooms
SGES - Replace exterior windows
Replace exterior windows
August 2021–design phase
SGES - Replace food service equipment
Replace food service equipment
August 2021–design phase
SGES - Secure entry upgrades
Secure entry upgrades
August 2021–design phase
SGES - Upgrade student restrooms and Interior finishes
Upgrade student restrooms and Interior finishes
August 2021–design phase
White Knoll Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
WKES - Add lane at bus drive
Add lane at bus drive
April 2019–design phase
WKES - Add storage/equipment building
Add storage/equipment building
April 2019–design phase
WKES - Future ready classrooms
Summer 2019–design phase
WKES - Future ready classrooms
WKES - Kindergarten addition
Kindergarten addition
April 2019–design phase
WKES - Replace fire alarm system
Replace fire alarm system
April 2019–design phase
WKES - Replace kitchen exhaust hood
Replace kitchen exhaust hood
April 2019–design phase
WKES - Secure entry upgrades
Secure entry upgrades
April 2019–design phase
WKES - Upgrade exterior windows
Upgrade exterior windows
April 2019–design phase
White Knoll High School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
WKHS - Interior Finish Upgrades
January 2019–design phase
WKHS - Interior Finish Upgrades
WKHS - Classroom addition
Classroom addition
January 2019–design phase
WKHS - Future ready classrooms
Future ready classrooms
Summer 2020–design phase
WKHS - Performing arts center
Performing arts center
January 2019–design phase
WKHS - Replace ceiling tiles in gym and cafeteria
Replace ceiling tiles in gym and cafeteria
January 2019–design phase
WKHS - Replace partial roof and HVAC
Replace partial roof and HVAC
January 2019–design phase
WKHS - Re-purpose of existing auditorium
Re-purpose of existing auditorium
January 2019–design phase
WKHS - Secure entry upgrades
Secure entry upgrades
January 2019–design phase
WKHS - Water heater replacement
Water heater replacement
January 2019–design phase
White Knoll Middle School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
WKMS - Add canopy at bus pick-up/drop off
Add canopy at bus pick-up/drop off
July 2019–design phase
WKMS - Add storage/equipment building
Add storage/equipment building
July 2019–design phase
WKMS - Future ready classrooms
Future ready classrooms
Summer 2020–design phase
WKMS - Replace ceiling tiles, interior lighting, carpet and toilet partitions
Replace ceiling tiles, interior lighting, carpet and toilet partitions
July 2019–design phase
WKMS - Replace exit lights and add exterior lighting
Replace exit lights and add exterior lighting
July 2019–design phase
WKMS - Update student restrooms
Update student restrooms
July 2019–design phase


314 Main St. Gilbert

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
GES - Selective demolition and repurposing
Selective demolition and repurposing
Dec. 2019–design phase
702 North Lake Dr. Lexington

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
NLD - Selective demolition and repurposing existing site
Selective demolition and repurposing existing site
Nov. 2020–design phase
758 Magnolia St. Pelion

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
MS - Selective demolition and re-purpose of existing site
Selective demolition and re-purpose of existing site
April 2020–design phase
Maintenance Facility

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
MF - Partial roof replacement
Partial roof replacement
March 2019–design phase
New River Bluff Area Elementary School

This project has been delayed as the district continues to seek a site for the project.

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
NRBAES - Future ready classrooms
Future ready classrooms
Summer 2019–design phase
NRBAES - New facility, secured entry
New facility, secured entry
June 2019–design phase
NRBAES - Opening year
Opening year
2022–2023
New Transportation Facility

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
NTF - New facility
New facility
Sept. 2019–design phase
New White Knoll Area Elementary School #19

Progress:
Lexington District One enters into option agreement
Lexington District One Board approves purchase of White Knoll property

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
NWKAES - Future ready classrooms
Future ready classrooms
August 2021–design phase
NWKAES - New facility, secured entry
New facility, secured entry
August 2021–design phase
NWKAES - Opening year
Opening year
2023–2024