2018–2023 BUILDING PLAN Progress


On November 6, 2018, Lexington County School District One voters, with more than 56% of the vote, voted for and passed a $365 million five-year building plan (2018–2023) that ensures that we can continue to offer our students the facilities they need now and in the future. 

This building plan includes updated safety and security systems at all district schools and facilities; three new schools to replace old schools and increase student capacity; two new elementary schools needed to accommodate student growth; renovations, additions and/or upgrades to 14 elementary schools, five middle schools, five high schools, the district's maintenance facility, technology center and community learning center; a new district transportation facility; and information technology equipment and furniture for Future Ready Classrooms at all schools.

Since the district understands that those same voters want to keep up with the progress of the building plan, we developed this webpage to do just that. This site enables voters to see what is currently happening at their child’s school and includes “before” photographs, the current phase taking place, photographs of that progress, etc. In fact, voters can click on the initials of their child’s school below and go directly to that school’s progress update.


What’s happening now?

       
 

03-05-2019

02-05-2019

02-05-2019

 

District administrators begin Transportation Facility land purchase negotiations. Read more here.

District administrators to begin land purchase negotiations, sell bonds. Read more here.

District hires six 2018–2023 building plan architects. Read more here.

Click here for past news articles.
Click here for Architectural Selection Committee Meeting Minutes.

FAQs

Want to know how the projects impact your child’s school and community?


What’s happening at my location?

CSES, CSMS, DES, FPES, GES, GHS, GMS, GPS, LMES, LES, LHS, LMS, LTC, MGES, MGMS, MES, NPES, OGES, PES, PHS, PMS, PHES, PHMS, RBES, RBHS, RCES, SGES, WKES, WKHS, WKMS

New elementary school #17 in Gilbert attendance area
New elementary school #18 in River Bluff attendance area
New elementary school #19 in White Knoll attendance area
New middle school in Pelion attendance area
New middle school in Lexington attendance area
New transportation facility
Maintenance facility
Rosenwald Community Learning Center


Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

January 2019–design phase

 

 


 
                   

 

Bus canopy/sitework improvements

 

January 2019–design phase

 

 

 
                   

 

Upgrade interior finish

 

January 2019–design phase

 


 
                   
 

Replace folding partition and
flooring in multi–purpose room 

 

January 2019–design phase 

         
                   


 

New storage/equipment building

 

January 2019–design phase

   
                   
   

Water heater replacement 

 

January 2019–design phase 

         
                   

 

Future ready classrooms

 

Summer 2019–design phase

   

  

 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

April 2020–design phase

   


 
                   

 

Classroom addition

April 2020–design phase


         

 

New storage/equipment building

 
April 2020–design phase
 


 
                   


 

Lane widening

 

April 2020–design phase


   
                   

 

Additional bus drop canopy

 

April 2020–design phase

       
     
   
         

 

New fire alarm system and
cafeteria lighting

 
April 2020–design phase
         
 

Future ready classrooms

Summer 2020–design phase

 
 


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

January 2019–design phase

 

 


 
                   

 

Future ready classrooms

 

Summer 2019–design phase

 

 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

Sept. 2020–design phase

 

 


 
                   

 

Classroom addition

 

Sept. 2020–design phase

 

 

 
                   
 

 Replace folding partition and
flooring in multi–purpose room

 

Sept. 2020–design phase

         
                   
   

Add exterior lighting in
front parking area 

 

Sept. 2020–design phase 

         
                   

 

New storage/equipment building

 

Sept. 2020–design phase

   


 
                   


 

Future ready classrooms

 

Summer 2019–design phase

     

See more here.


Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Selective demolition and repurposing

 

Dec. 2019–design phase

 


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

February 2019–design phase

   


 
                   

 

Program–based additions needed;
PAC, weight, wrestling

 

February 2019–design phase

 

 

 
                   
 

Upgrade interior/exterior lighting 

 

February 2019–design phase 

         
                   
 

Add exterior hardscapes 

 

February 2019–design phase 

         
                   
 

Interior & Exterior finish upgrade 

 

February 2019–design phase 

         
                   
 

Fire alarm system replacement

 

February 2019–design phase

   


 
                   

 

Future ready classrooms

 

Summer 2020–design phase

     

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   
 

 Interior finish upgrades

 

 June 2020–design phase

         
                   

 

Canopy needed at front entrance

 

June 2020–design phase


 


 
                   

 

Exterior security lighting upgrades

 

June 2020–design phase

 

 

 

                   

 

Classroom addition

June 2020–design phase

 

 


 

                   
 

New dishwasher, cooler, freezer 

 

June 2020–design phase 

         
                   

 

Fire alarm system replacement

 

June 2020–design phase

 

 

 


                 


 

Additional visitor parking

 

June 2020–design phase

   


 
                   
   

Future ready classrooms

  Summer 2020–design phase
         
See more here.
Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

Dec. 2018–design phase

 

 


 
                   

 

Replace wood doors and add
ADA compliant door hardware

 

Dec. 2018–design phase

   

 
                   
 

Student restrooms renovation,
ADA upgrades

 

Dec. 2018–design phase

   


 
                   
 

Car/bus circulation updated

 

Dec. 2018–design phase

     
                   
 

HVAC controls improvement,
water heater, exhaust hood

 

Dec. 2018–design phase

         
                   
 

Upgrade interior/exterior lighting

 

Dec. 2018–design phase

         
                   
   

Upgrade interior finish

 

Dec. 2018–design phase

         
                   

 

 Addition to existing storage/
equipment building

 

 Dec. 2018–design phase

         
                   
 

 Add exterior canopies, walking
track and hardscapes

 

 Dec. 2018–design phase

         
                   

 

Future ready classrooms

 

Summer 2019–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Roof replacement

 

Sept. 2020–design phase

 

 


 
                   
 

Upgrade interior finish

 

Sept. 2020–design phase

 

 

 
                   
 

Upgrade cafeteria and stage lighting

             
                   
 

Storage/equipment building

Sept. 2020–design phase

 

 


 
                   
   

Upgrade exterior lighting,
terraced wall, and hardscaping

 

 Sept. 2020–design phase

         
                   
 

ADA upgrades to restrooms 

 

Sept. 2020–design phase 

         
                   

 

Future ready classrooms

 

Summer 2019–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

May 2021–design phase

   


 
                   
 

Replace wood doors and add
ADA compliant door hardware

 

May 2021–design phase

   

 
                   
 

New drop off/pick–up lanes 

 

May 2021–design phase

         
                   
 

Upgrade interior finish

 

May 2021–design phase

   


 
                   

 

Upgrade exterior lighting 

 

 May 2021–design phase

         
                   
 

Demolish and remove old buildings

 

May 2021–design phase

     
                   
 

Replace casework

 

May 2021–design phase

         
                   
 

Storage/equipment building 

 

May 2021–design phase

         
                   

 

Future ready classrooms

 

Summer 2019–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

Nov. 2018–design phase

   


 
                   

 

Replace classroom carpet

 

Nov. 2018–design phase

   

 
                   
 

Roof replacement

 

Nov. 2018–design phase

   


 
                   
 

New athletic storage buildings (2)

 

Nov. 2018–design phase

     
                   
   

New asphalt overlay

 

Nov. 2018–design phase

         
                   
   

Upgrade interior finish and
new signage 

 

Nov. 2018–design phase

         
                   

 

Future ready classrooms

 

Summer 2020–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Selective demolition and
repurposing existing site

 

Nov. 2020–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

February 2019–design phase

   


 
                   
 

ADA restroom upgrades

 

February 2019–design phase

   

 
                   
 

Replace roll–up doors

 

February 2019–design phase

   


 
                   
   

Renovate locker rooms

 

February 2019–design phase 

         
                   

 

Replace carpet in administration
and cosmetology areas

 

February 2019–design phase 

         
                   
   

Add canopies at welding labs
and overlay asphalt at front 

 

February 2019–design phase 

         
                   
 

Replace old windows

 
February 2019–design phase
     
                   
 

Exterior painting 

 

February 2019–design phase 

         
                   

Future ready classrooms

 

Summer 2020–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

June 2022–design phase

   


 
                   

 

Add storage/equipment building

 

June 2022–design phase

     
                   

 

Future ready classrooms

Summer 2019–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

June 2022–design phase

   


 
                   
 

Add storage/equipment building

 

June 2022–design phase

     
                   

 

Future ready classrooms

 

Summer 2020–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Replace fire alarm system

 

June 2022–design phase

   


 
                   
 

Add storage/equipment building

 

June 2022–design phase

   

 
                   
 

Upgrade Interior/exterior lighting 

 

June 2022–design phase 

         
                   
 

Upgrade interior finish

 

June 2022–design phase

   


 
                   

 

Future ready classrooms

 

Summer 2019–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

Nov. 2022–design phase

   


 
                   
 

Update lighting controls

 

Nov. 2022–design phase

   

 
                   
 

Add storage/equipment building

 

Nov. 2022–design phase

     
                   
 

 Repaint Corridors,
Replace Folding Partition

 

 Nov. 2022–design phase

         
                   

 

Future ready classrooms

Summer 2019–design phase

   


 

See more here.


Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

May 2019–design phase

   


 
                   
 

Update student restrooms

 

May 2019–design phase

   

 
                   
 

New fire sprinkler system

 

May 2019–design phase

   


 
                   
 

Replace fire alarm 

 

May 2019–design phase

         
                   
   

 Classroom/Fine Arts addition

 

 May 2019–design phase

         
                   
 

 Sitework Improvements

 

May 2019–design phase 

         
                   
 

Add storage/equipment building

 

May 2019–design phase

     
                   

 

New exterior security lighting 

 

May 2019–design phase

         
                   

 

Future ready classrooms

 

Summer 2019–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Replace ceiling tiles
and interior lighting

 

July 2019–design phase

   


 
                   
 

Replace roof on latest addition

 

July 2019–design phase

   

 
                   

 

Replace carpet in chorus room

 

July 2019–design phase

   


 
                   
   

Replace serving lines in kitchen 

 

July 2019–design phase 

         
                   
 

Add storage/equipment building

 

July 2019–design phase

     
                   

 

Future ready classrooms

 

Summer 2019–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

Dec. 2018–design phase

   


 
                   

 

New track locker room,
concessions and restroom

 

Dec. 2018–design phase

   

 
                   
 

New weight/wrestling room 

 

Dec. 2018–design phase 

         
                   
 

Track modifications

 

Dec. 2018–design phase

   


 
                   
 

Add stadium visitor locker room

 

Dec. 2018–design phase

     
                   
 

Upgrade audio/lighting in auditorium 

 

Dec. 2018–design phase

         
                   
 

Upgrade lighting in gym 

 

Dec. 2018–design phase 

         
                   

 

Add school store in commons area 

 

Dec. 2018–design phase 

         
                   

 

Future ready classrooms

 

Summer 2020–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Selective demolition and
re-purpose of existing site

 

April 2020–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

August 2022–design phase

   


 
                   
 

Replace carpet with sports
flooring in the multi–purpose room

 

August 2022–design phase

   

 
                   
 

Replace carpet in admin/
foyer with hard tile

 

August 2022–design phase

   


 
                   
   

Replace folding partition

 

 August 2022–design phase

         
                   
 

Add storage/equipment building

 

August 2022–design phase

     
                   
   

Add kitchen loading dock

 

 August 2022–design phase

         
                   

 

Future ready classrooms

 

Summer 2019–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

Nov. 2022–design phase

   


 
                   

 

Add canopies and sidewalk

 

Nov. 2022–design phase

   


 
                   
 

Replace cafeteria lights

 

Nov. 2022–design phase

     
                   

 

Future ready classrooms

 

Summer 2020–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

July 2019–design phase

   


 
                   
 

Replace wood doors and add
ADA compliant door hardware

 

July 2019–design phase

   

 
                   
 

Upgrade student restrooms
and interior finishes

 

July 2019–design phase

   


 
                   
 

Add storage/equipment building

 

July 2019–design phase

     
                   
   

Replace food service equipment 

 

July 2019–design phase

 

       
                   

 

Future ready classrooms

 

Summer 2019–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

January 2022–design phase

   


 
                   
 

Upgrade parking lot landscaping

 

January 2022–design phase

   

 
                   
 

Upgrade student canopy

 

January 2022–design phase

   


 
                   

 

Future ready classrooms

 

Summer 2020–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

January 2019–design phase

   


 
                   

 

Future ready classrooms

 

Summer 2019–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

August 2021–design phase

   


 
                   
 

Replace exterior windows

 

August 2021–design phase

   

 
                   
 

Replace food service equipment

 

August 2021–design phase

   


 
                   
 

Upgrade student restrooms
and Interior finishes 

 

August 2021–design phase 

         
                   
 

Add storage/equipment building

 

August 2021–design phase

     
                   


Future ready classrooms

 

Summer 2019–design phase

   


 

See more here.

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

April 2019–design phase

   


 
                   
 

Kindergarten addition

 

April 2019–design phase

   

 
                   
 

Upgrade exterior windows

 

April 2019–design phase

   


 
                   
 

Add lane at bus drive

 

April 2019–design phase

     
                   
   

Replace fire alarm system

 

April 2019–design phase

 

 

 

 

 

                   

 

 Add storage/equipment building

 

April 2019–design phase 

         
                   

 

Replace kitchen exhaust hood

 

April 2019–design phase

         
                   

 

Future ready classrooms

 

Summer 2019–design phase

   


 

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Secure entry upgrades

 

January 2019–design phase

   


 
                   
 

Classroom addition

 

January 2019–design phase

   

 
                   
 

Replace ceiling tiles in
gym and cafeteria

 

 January 2019–design phase

         
                   
 

Re-purpose of existing auditorium

 

January 2019–design phase 

         
                   
 

Water heater replacement

 

 January 2019–design phase

         
                   
 

Performing arts center

 

January 2019–design phase

   


 
                   
 

Replace partial roof and HVAC

 

January 2019–design phase

     
                   

 

Future ready classrooms

 

Summer 2020–design phase

   


 

Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

Update student restrooms

 

July 2019–design phase

   
                   

 

Replace exit lights and
add exterior lighting 

 

July 2019–design phase 

         
                   

 

Add canopy at bus pick-up/drop off

 

July 2019–design phase

   

 
                   
 

Replace ceiling tiles, interior
lighting, carpet and toilet partitions

 

July 2019–design phase

   


 
                   
 

Add storage/equipment building

 

July 2019–design phase

     
                   

 

Future ready classrooms

 

Summer 2020–design phase

   


 




Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

New facility, secured entry

 

Nov. 2018–design phase

   


 
                   
 

Future ready classrooms

 

Summer 2019–design phase

   

 


Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

New facility, secured entry

 

June 2019–design phase

   


 
                   

 

Future ready classrooms

 

Summer 2020–design phase

   


 


Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

New facility, secured entry

 

Nov. 2018–design phase

   


 
                   

 

Future ready classrooms

 

Summer 2020–design phase

   


 



Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

New facility, secured entry

 

June 2019–design phase

   


 
                   

 

Future ready classrooms

 

Summer 2019–design phase

   


 


Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   

 

New facility, secured entry

 

August 2021–design phase

   


 
                   

 

Future ready classrooms

 

August 2021–design phase

   


 


Before Photo   Project   Anticipated Start Date   Current Photo   Completed Date  
                   
   

 New facility

 

Sept. 2019–design phase